Addressing electricity supply shortages in Rwanda

Rwanda’s electricity generation capacity increased from 41MW in 2004 to 75MW by 2010 and load shedding going from approximately 50 percent at peak hours in 2004 to zero percent in 2010. The Rwanda’s Urgent Electricity Rehabilitation Project (UERP) through the International Development Association (IDA) funds and expertise have contributed to addressing the severe power shortages in Rwanda by financing the construction of a new 21 megawatt (MW) power plant (Jabana HFO [Heavy Fuel Oil] Power Plant).
Businesses in Rwanda do not have to operate costly diesel generator sets due to zero percent power cuts.
Businesses in Rwanda do not have to operate costly diesel generator sets due to zero percent power cuts.
Times Reporter